PBF has reportedly pushed Chalmette’s crude unit and coker into 2027, and CITGO has done the same with the Lake Charles coker[2]. Meanwhile Gulf Coast plants that ran hard in 2026 are running API 510, 570, 653, 580 and 581 inspection intervals to their allowable limits, and coker drum inspections are among the jobs expected to grow[1]. The workforce that does this repair is small: BLS counts 10,200 boilermaker jobs nationwide, projected to decline 2% from 2025 to 2035, with about 700 openings a year[3]. Plan for coker and boiler scopes to set the schedule.
01.Why cokers and boilers set the critical path
The critical path is the chain of tasks that sets the end date. Heavy, thick-walled equipment tends to sit on it because the work is slow and sequential: cool down, open, clean, inspect, repair, re-inspect, close and test. Inspection findings often add repair scope only after the equipment is open (our engineering summary).
| Equipment | Typical turnaround work | Why it is slow |
|---|---|---|
| Coke drums | Internal inspection, crack and bulge assessment, weld repair, skirt and nozzle work | Thermal cycling damage is found only after cleaning; repairs need qualified procedures and heat treatment |
| Coker heater | Tube inspection, decoking, tube replacement | Long-lead tubes; many welds |
| Boilers | Tube inspection and replacement, drum and header inspection | Many tube welds by qualified welders; jurisdictional inspection before return to service |
| Fractionator and piping | Internals, corrosion inspection, piping replacement | Access, scaffolding and confined-space entry |
Our engineering summary of common scopes. Each site’s inspection plan sets the actual work.
Running harder makes this worse. BIC Magazine notes that heavy, high-sulfur, high-metals Venezuelan crude run through cokers and hydrocrackers since early 2026 speeds up coke buildup and fouling, and expects coker drum inspections and fired heater tube inspections to bring more work than planned[1].
02.Which coker work has moved
| Site | What moved | Reported timing |
|---|---|---|
| PBF Chalmette (LA) | Crude unit and coker | Into 2027[2] |
| CITGO Lake Charles (LA) | Coker | Into 2027[2] |
| Motiva Port Arthur (TX) | Major turnaround including largest crude unit | Fall 2027 (see season outlook) |
| ExxonMobil Beaumont (TX) | FCC and at least two hydrotreaters | About 45 days, early Dec 2026 to mid-Jan 2027[2] |
As reported by Breakwave Advisors (Aug 31, 2026). Companies rarely publish turnaround dates; treat these as reported, not confirmed.
Inspection intervals do not reset because margins are high. BIC points out that mandatory scope is driven by run time and unit history, not by crack spreads[1]. A coker deferred for a year usually comes back with the same or more scope.
03.Inspection and repair rules that shape the work
| Code or rule | Covers | What it means on the job |
|---|---|---|
| OSHA 29 CFR 1910.119(j) | Mechanical integrity in process safety management | Inspection and testing must follow recognized engineering practice[6] |
| API 510 | In-service pressure vessels: inspection, repair, alteration, rerating | Coke drums and other vessels; work signed off by a certified inspector[4] |
| API 570 | In-service metallic piping: inspection, repair, alteration | Coker and boiler feed piping[5] |
| National Board Inspection Code | Boiler and pressure-vessel repairs in most U.S. jurisdictions | Repairs by an authorized repair organization, accepted by the jurisdiction’s inspector (general practice; confirm locally) |
Inspector supply matters as much as craft supply. API 510 and API 570 certification each require one to five years of relevant experience depending on education, a 7.5-hour exam, and recertification every three years with at least 20% of recent time spent on inspection work[4][5]. Certified inspectors cannot be hired at short notice.
04.The boilermaker squeeze in numbers
| Area | Boilermaker jobs | Mean hourly wage | Median hourly wage |
|---|---|---|---|
| Houston | 1,170 | $37.10 | $37.06 |
| Beaumont-Port Arthur | 230 | $35.99 | $35.13 |
| Baton Rouge | 680 | $34.65 | $35.93 |
| Lake Charles | Not published | — | — |
| United States | 10,200 | — | $36.74 ($76,410 a year) |
BLS OEWS, May 2025[7]; national figures from the Occupational Outlook Handbook[3]. OEWS wages are straight-time pay and exclude overtime and per diem[8].
The local counts are small: about 2,000 boilermaker jobs across Houston, Beaumont-Port Arthur and Baton Rouge combined[7]. A single large coker or boiler outage can call for crews in the dozens to hundreds, so travelers fill the gap, and they go where the work pays best (our assessment). Apprenticeships typically last four years[3], so new supply cannot be trained between now and 2027.
05.What owners, contractors and crafts can do
| Who | Action |
|---|---|
| Owners | Treat coker drum and boiler inspections as known scope with a repair allowance, not as discovery; secure long-lead tubes and drum repair materials early |
| Planners | Phase deferred units rather than stacking them, as Breakwave suggests refiners may do in early 2027[2] |
| Contractors | Lock in boilermaker crews and certified inspectors before scopes are final; check welder qualifications for chrome-moly and heat-treatment work |
| Boilermakers and welders | Keep pressure-welding qualifications and site credentials current (gate credentials guide) |
Our recommendations, based on the cited reporting and data.
For how labor and long-lead parts interact with new construction, see capex vs. turnarounds; for the coker control-room pilot at Port Arthur, see AI in the control room.
06.Frequently Asked Questions
Why are cokers often on the turnaround critical path?
Coke drums and coker heaters need slow, sequential work: cooling, cleaning, inspection and weld repair. Damage from thermal cycling is often found only after the drums are open, which adds repair scope late.
Which Gulf Coast cokers were deferred to 2027?
Breakwave Advisors reported in August 2026 that PBF pushed Chalmette's crude unit and coker into 2027 and that CITGO did the same with the Lake Charles coker. The companies have not published dates.
How many boilermakers are there in the U.S.?
BLS counts 10,200 boilermaker jobs in 2025, projected to decline 2% from 2025 to 2035, with about 700 openings a year.
What do boilermakers earn on the Gulf Coast?
BLS May 2025 data show mean hourly wages of $37.10 in Houston, $35.99 in Beaumont-Port Arthur and $34.65 in Baton Rouge. These are straight-time wages and exclude overtime and per diem.
What is the difference between API 510 and API 570?
API 510 covers in-service pressure vessels and API 570 covers in-service metallic piping, including their inspection, repair and alteration. Each has its own inspector certification renewed every three years.
Sources
- [1] BIC Magazine — The clock doesn’t care about crack spreads (Sep 1, 2026)
- [2] Breakwave Advisors — No margin for error (Aug 31, 2026)
- [3] U.S. BLS — Occupational Outlook Handbook: Boilermakers
- [4] American Petroleum Institute — API 510 Pressure Vessel Inspector certification
- [5] American Petroleum Institute — API 570 Piping Inspector certification
- [6] OSHA — 29 CFR 1910.119, Process safety management: mechanical integrity
- [7] U.S. BLS — Occupational Employment and Wage Statistics, May 2025 metropolitan area estimates (Beaumont-Port Arthur, Houston, Lake Charles, Baton Rouge)
- [8] U.S. BLS — Technical Notes for May 2025 OEWS Estimates
All sources accessed November 16, 2026. Figures are as published by each source; confirm with the site or your employer before you commit crews or travel.