Experienced planners freeze turnaround scope roughly 9–12 months before the outage, or 16–18 months when a significant capital project is tied in[1]; ExxonMobil Baytown has described a work list called final about 16 months out[2]. During the event, OSHA’s process safety standard still applies in full: contractor safety, pre-startup safety review, mechanical integrity, hot work permits and management of change[3], plus lockout/tagout under 29 CFR 1910.147[4]. Temporary trailers and portable buildings are sited under API RP 753[6], a practice tightened after the 2005 Texas City explosion[7]. Download the checklist below as CSV.
01.Milestones from T-24 months to the post-turnaround review
| When | Milestone | Source |
|---|---|---|
| T-32 months | First reviews when many major capital projects are planned for the outage | Hernjak, ExxonMobil Baytown[2] |
| About T-24 months | Operations (linemen) review, then a preliminary work scope | Hernjak[2] |
| About T-18 months | Prep review of the work list | Hernjak[2] |
| T-16 to T-18 months | Work list called final when a significant capital project is integrated | Hernjak[2]; Olsen[1] |
| T-9 to T-12 months | Common scope freeze when no major capital project is included | Olsen[1] |
| After freeze | Detailed planning, long-lead materials and spare parts, contractor resourcing | Olsen[1] |
| Before startup | Pre-startup safety review for new or significantly modified equipment | OSHA 1910.119(i)[3] |
| Within 2 months after | Post-turnaround review to feed the next event | Hernjak[2] |
Timings are published examples from industry practice, not a regulatory schedule. Your site’s turnaround procedure governs.
Olsen notes that discovery work, found only when equipment is opened, is the largest contributor to scope growth[1]. An early, firm freeze leaves time to plan for the known and anticipated scope, so discovery is the only surprise. See contracting models for how scope type affects contracts.
02.OSHA process safety elements that apply during a turnaround
| PSM element | What it requires | Turnaround checklist item |
|---|---|---|
| Contractors, 1910.119(h) | Owner evaluates contractor safety performance; contractors train their workers on hazards and the emergency plan[3] | Contractor safety prequalification and site orientation records on file |
| Pre-startup safety review, 1910.119(i) | Review before introducing highly hazardous chemicals to new or significantly modified equipment[3] | PSSR signed for every modified system before startup |
| Mechanical integrity, 1910.119(j) | Inspection and testing per recognized and generally accepted good engineering practice[3] | Inspection plan tied to API 510 / 570 / 653 intervals |
| Hot work permit, 1910.119(k) | Permit for hot work on or near covered processes[3] | Hot work permit system, gas testing, fire watch staffing |
| Management of change, 1910.119(l) | Written procedures for changes to chemicals, technology, equipment and procedures[3] | MOC closed for every scope item that changes the design |
Summarized from 29 CFR 1910.119. Read the full text for the exact obligations.
Lockout/tagout runs alongside PSM. OSHA’s control of hazardous energy standard requires an energy control program, procedures and periodic inspections whenever servicing could expose workers to unexpected energization or release of stored energy[4]. For large outages, a group lockout procedure and a single isolation register are the usual way to keep control (our assessment).
03.Temporary buildings and trailers: API RP 752 and 753
Turnarounds bring trailers, tool cribs and break areas close to process units. API splits building siting between RP 752 for permanent buildings and RP 753 for portable buildings[5][6], and new editions of the facility siting standards were released in January 2024[8].
After the 2005 BP Texas City explosion, the U.S. Chemical Safety Board noted that trailers used for short periods, such as turnaround trailers, had been treated as posing little danger under the site’s siting policy, and recommended changes to the API practice[7]. Treat every turnaround trailer location as a siting decision, not a logistics one.
- Keep non-essential people out of portable buildings in or near process areas, as RP 753 advises[6].
- Site trailers and tents from the plant’s blast and fire hazard maps before the outage, not on the day crews arrive.
- Re-check siting when scope or unit status changes during the event (our recommendation).
04.The checklist (download as CSV)
| Phase | Item | Owner |
|---|---|---|
| Scope | Work list frozen; late additions only through change control | Turnaround manager |
| Scope | Each item classified as known, anticipated or discovery | Planning |
| Materials | Long-lead items ordered with delivery dates before mobilization | Procurement |
| Contractors | Safety prequalification, orientation and credential checks complete | Contractor coordinator |
| Safety | Group lockout plan and isolation register ready | Operations |
| Safety | Hot work permit and gas testing staffing confirmed | Safety |
| Siting | Trailer and tent locations approved against API RP 753 siting study | Process safety |
| Inspection | API 510 / 570 / 653 inspection scope and inspectors booked | Inspection |
| MOC | All design changes have approved MOCs | Engineering |
| Startup | PSSR completed for new or modified equipment | Operations |
| Closeout | Post-turnaround review scheduled within two months | Turnaround manager |
Our consolidated checklist from the cited sources. Download CSV and adapt it to your site.
For the workforce side, see plant-gate credentials and craft pay by metro. For equipment that tends to set the schedule, see cokers and boilers on the critical path.
05.Frequently Asked Questions
How far ahead should a refinery turnaround be planned?
Published practice puts first reviews up to about 32 months ahead when major capital projects are involved, a final work list around 16 to 18 months ahead in that case, and a scope freeze about 9 to 12 months ahead otherwise.
Which OSHA rules apply during a turnaround?
The process safety management standard (29 CFR 1910.119) still applies, including contractor safety, pre-startup safety review, mechanical integrity, hot work permits and management of change, along with lockout/tagout under 29 CFR 1910.147.
When is a pre-startup safety review required?
Under 29 CFR 1910.119(i), before highly hazardous chemicals are introduced to new facilities or to modified facilities when the change is significant enough to require a change in process safety information.
Do turnaround trailers need a siting study?
Yes. API RP 753 covers portable buildings near process areas. The Chemical Safety Board's Texas City investigation criticized treating short-term turnaround trailers as low risk.
Can I download this checklist?
Yes. A CSV version is linked on the page and can be opened in Excel or Google Sheets.
Sources
- [1] Tim Olsen, Emerson — Turnarounds: Strategic opportunities to improve, Chemical Engineering Progress (Aug 2018)
- [2] BIC Magazine — Quality work scopes imperative for turnaround success (2015), quoting Jim Hernjak, ExxonMobil Baytown
- [3] OSHA — 29 CFR 1910.119, Process safety management of highly hazardous chemicals
- [4] OSHA — 29 CFR 1910.147, The control of hazardous energy (lockout/tagout)
- [5] American Petroleum Institute — RP 752, Management of hazards associated with location of process plant permanent buildings
- [6] American Petroleum Institute — RP 753, Management of hazards associated with location of process plant portable buildings
- [7] U.S. Chemical Safety Board — BP Texas City recommendations
- [8] American Petroleum Institute — API releases new updates to standards for hazard management in process plant structures (Jan 16, 2024)
All sources accessed November 21, 2026. General guidance, not a substitute for your site’s procedures, legal advice or a qualified process safety review.