Time-and-materials (T&M) is the default for turnarounds because discovery work makes a fixed price impractical, but it carries the most risk for the owner unless it is capped with negotiated rates, maximum hours, material markup limits and a maximum total cost[1]. Target-price contracts share overruns and savings between owner and contractor in pre-agreed bands[4][5]. Benchmark data show the real problem is scope: AP-Networks found 133 refinery turnarounds overran their control budgets by 14% on average, citing poor scope control and discovery among the causes[2].
01.The three models side by side
| Model | How the contractor is paid | Who carries overrun risk | Fits when |
|---|---|---|---|
| Time & materials (T&M) | Hours at agreed rates plus materials and markup | Mostly the owner[1] | Scope is uncertain and discovery is likely |
| T&M with caps | As above, with maximum hours, markup limits and a cost ceiling[1] | Shared up to the cap | Owner wants T&M flexibility with limits |
| Target price (pain/gain) | Actual cost plus fee; difference from target shared in agreed bands[4][5] | Shared by formula | Scope is well defined and cost records are reliable |
| Lump sum (fixed price) | Fixed price for defined scope | Mostly the contractor | Defined work packages, such as a tie-in or a capital project[1] |
Our comparison, based on the cited sources. Actual terms vary by contract.
A 2018 Chemical Engineering Progress article by Emerson’s Tim Olsen explains why lump sum is rare for turnarounds: there is a high probability of discovery work, meaning work that was unknown or only suspected until equipment or piping is opened. That, he writes, is why turnarounds use T&M, while integrated capital projects may still be lump-sum turnkey[1].
02.What the benchmark data say about overruns
| Finding | Figure | Source |
|---|---|---|
| Average overrun vs. control budget, 133 refinery turnarounds | 14% | AP-Networks, via Reliability Academy[2] |
| Actual estimate accuracy | Closer to ±25% than the assumed ±10% | Same[2] |
| Turnarounds exceeding plan by 10% or tripping soon after startup (1,350+ events) | More than two-thirds | Same[2] |
| Overrunning by more than 30% (same database) | 40% | Same[2] |
| Largest contributor to scope growth | Discovery work | Olsen, CEP[1] |
AP-Networks data as reported by Reliability Academy (Aug 24, 2026); the article notes a widely cited 80%-over-budget figure could not be traced.
You may see “T&M contracts overrun 20–35%” quoted as a rule. We found no study that ties an overrun range to a contract type. The figures above describe turnarounds in general, and the causes cited are scope control, discovery, planning and unrealistic targets[2].
03.Scope freeze: the lever that matters most
Olsen reports that many refiners freeze turnaround scope 9–12 months ahead, extending that to 16–18 months when a significant capital project is part of the event, to allow time for planning and long-lead parts[1]. ExxonMobil Baytown’s turnaround manager described a similar sequence at an AFPM conference: a prep review about 18 months out, a work list called final about 16 months out, then a harder freeze later[3].
| Scope type | Example | How to handle it in the contract |
|---|---|---|
| Known | Planned exchanger bundle replacement | Firm quantities and rates; candidate for lump-sum packages |
| Anticipated | Likely weld repairs on a coke drum | Allowance with pre-agreed unit rates |
| Discovery | Corrosion found when a line is opened | T&M with change control and approval limits |
Scope categories follow Olsen (CEP, 2018)[1]; contract handling is our recommendation.
04.How target-price sharing works
In a target-price contract, the contractor is paid its actual cost plus a fee, and the final cost is compared with an agreed target. Savings and overruns are split in pre-agreed percentages, often in bands, so the contractor keeps a smaller share of very large savings and bears a larger share of very large overruns[4][5]. The UK NEC4 Option C is a widely used published form of this model[5].
- The target must move with approved changes. If the target is not adjusted for each approved change, the sharing calculation breaks down[4].
- Cost records must be reliable. Disputes over what counts as allowable cost are a known weak point[4].
- It works best on defined scope. Heavy discovery makes a fair target hard to set (our assessment).
05.A checklist for 2027 turnaround contracts
- Freeze scope early and hold to it; record late additions as changes with cost and schedule impact[1][3].
- Use T&M for discovery, but cap it: negotiated rates, maximum hours, material markup and a maximum total[1].
- Carve out defined packages, such as heater re-tubes or tie-ins, for lump-sum or target-price terms.
- Agree how rates change if the season gets tight. Deferred work is stacking up for 2027; see the season outlook.
- Include date-shift terms, since outage dates move (see turnaround timing).
Our recommendations. Not legal advice; have contracts reviewed by counsel.
06.Frequently Asked Questions
Why are refinery turnarounds usually time and materials?
Because of discovery work: damage found only when equipment is opened. A fixed price for unknown work is impractical, so owners use time and materials and control it with negotiated rates, hour limits, markup limits and a cost ceiling.
What is a target-price contract with pain/gain share?
The contractor is paid actual cost plus a fee, and the difference between final cost and an agreed target is shared between owner and contractor in pre-agreed percentages, often in bands.
How often do turnarounds go over budget?
AP-Networks data reported in 2026 show 133 refinery turnarounds overran their control budgets by 14% on average, and in a database of more than 1,350 events, 40% overran by more than 30%.
When should turnaround scope be frozen?
Many refiners freeze scope 9 to 12 months ahead, and 16 to 18 months when a large capital project is included, according to a 2018 Chemical Engineering Progress article.
Is lump sum ever used in turnarounds?
Yes, for well-defined packages and for capital projects executed during the outage. It is rarely used for the turnaround as a whole because of discovery work.
Sources
- [1] Tim Olsen, Emerson — Turnarounds: Strategic opportunities to improve, Chemical Engineering Progress (Aug 2018)
- [2] Reliability Academy — Why do maintenance shutdowns overrun? The 6 real causes (Aug 24, 2026), citing AP-Networks
- [3] BIC Magazine — Quality work scopes imperative for turnaround success (Aug 2015)
- [4] Rimkus — Navigating NEC4 Option C: A contractor’s guide to practical realities and pitfalls
- [5] NEC — NEC4 Engineering and Construction Contract, Option C: target contract with activity schedule
All sources accessed November 16, 2026. General information, not legal advice. Figures are as published by each source.