Turnaround Contracting Models: Time & Materials vs. Target Price vs. Lump Sum, and Why Scope Freeze Matters More

When a turnaround runs over, the contract usually gets the blame. The evidence points somewhere else: to scope that was not frozen in time and to discovery work found after equipment is opened. Contract type matters, but mostly in how it handles those two risks.

Published November 16, 2026 · Data checked November 16, 2026 · 5 cited sources

Average budget overrun (133 refinery TARs)
14%
Overrun >30% (AP-Networks database)
40%
Common scope freeze
9–12 months out
With a big capital project
16–18 months
Short answer

Time-and-materials (T&M) is the default for turnarounds because discovery work makes a fixed price impractical, but it carries the most risk for the owner unless it is capped with negotiated rates, maximum hours, material markup limits and a maximum total cost[1]. Target-price contracts share overruns and savings between owner and contractor in pre-agreed bands[4][5]. Benchmark data show the real problem is scope: AP-Networks found 133 refinery turnarounds overran their control budgets by 14% on average, citing poor scope control and discovery among the causes[2].

01.The three models side by side

ModelHow the contractor is paidWho carries overrun riskFits when
Time & materials (T&M)Hours at agreed rates plus materials and markupMostly the owner[1]Scope is uncertain and discovery is likely
T&M with capsAs above, with maximum hours, markup limits and a cost ceiling[1]Shared up to the capOwner wants T&M flexibility with limits
Target price (pain/gain)Actual cost plus fee; difference from target shared in agreed bands[4][5]Shared by formulaScope is well defined and cost records are reliable
Lump sum (fixed price)Fixed price for defined scopeMostly the contractorDefined work packages, such as a tie-in or a capital project[1]

Our comparison, based on the cited sources. Actual terms vary by contract.

A 2018 Chemical Engineering Progress article by Emerson’s Tim Olsen explains why lump sum is rare for turnarounds: there is a high probability of discovery work, meaning work that was unknown or only suspected until equipment or piping is opened. That, he writes, is why turnarounds use T&M, while integrated capital projects may still be lump-sum turnkey[1].

02.What the benchmark data say about overruns

FindingFigureSource
Average overrun vs. control budget, 133 refinery turnarounds14%AP-Networks, via Reliability Academy[2]
Actual estimate accuracyCloser to ±25% than the assumed ±10%Same[2]
Turnarounds exceeding plan by 10% or tripping soon after startup (1,350+ events)More than two-thirdsSame[2]
Overrunning by more than 30% (same database)40%Same[2]
Largest contributor to scope growthDiscovery workOlsen, CEP[1]

AP-Networks data as reported by Reliability Academy (Aug 24, 2026); the article notes a widely cited 80%-over-budget figure could not be traced.

Correcting a common claim

You may see “T&M contracts overrun 20–35%” quoted as a rule. We found no study that ties an overrun range to a contract type. The figures above describe turnarounds in general, and the causes cited are scope control, discovery, planning and unrealistic targets[2].

03.Scope freeze: the lever that matters most

Olsen reports that many refiners freeze turnaround scope 9–12 months ahead, extending that to 16–18 months when a significant capital project is part of the event, to allow time for planning and long-lead parts[1]. ExxonMobil Baytown’s turnaround manager described a similar sequence at an AFPM conference: a prep review about 18 months out, a work list called final about 16 months out, then a harder freeze later[3].

Scope typeExampleHow to handle it in the contract
KnownPlanned exchanger bundle replacementFirm quantities and rates; candidate for lump-sum packages
AnticipatedLikely weld repairs on a coke drumAllowance with pre-agreed unit rates
DiscoveryCorrosion found when a line is openedT&M with change control and approval limits

Scope categories follow Olsen (CEP, 2018)[1]; contract handling is our recommendation.

04.How target-price sharing works

In a target-price contract, the contractor is paid its actual cost plus a fee, and the final cost is compared with an agreed target. Savings and overruns are split in pre-agreed percentages, often in bands, so the contractor keeps a smaller share of very large savings and bears a larger share of very large overruns[4][5]. The UK NEC4 Option C is a widely used published form of this model[5].

  • The target must move with approved changes. If the target is not adjusted for each approved change, the sharing calculation breaks down[4].
  • Cost records must be reliable. Disputes over what counts as allowable cost are a known weak point[4].
  • It works best on defined scope. Heavy discovery makes a fair target hard to set (our assessment).

05.A checklist for 2027 turnaround contracts

  • Freeze scope early and hold to it; record late additions as changes with cost and schedule impact[1][3].
  • Use T&M for discovery, but cap it: negotiated rates, maximum hours, material markup and a maximum total[1].
  • Carve out defined packages, such as heater re-tubes or tie-ins, for lump-sum or target-price terms.
  • Agree how rates change if the season gets tight. Deferred work is stacking up for 2027; see the season outlook.
  • Include date-shift terms, since outage dates move (see turnaround timing).

Our recommendations. Not legal advice; have contracts reviewed by counsel.

06.Frequently Asked Questions

Why are refinery turnarounds usually time and materials?

Because of discovery work: damage found only when equipment is opened. A fixed price for unknown work is impractical, so owners use time and materials and control it with negotiated rates, hour limits, markup limits and a cost ceiling.

What is a target-price contract with pain/gain share?

The contractor is paid actual cost plus a fee, and the difference between final cost and an agreed target is shared between owner and contractor in pre-agreed percentages, often in bands.

How often do turnarounds go over budget?

AP-Networks data reported in 2026 show 133 refinery turnarounds overran their control budgets by 14% on average, and in a database of more than 1,350 events, 40% overran by more than 30%.

When should turnaround scope be frozen?

Many refiners freeze scope 9 to 12 months ahead, and 16 to 18 months when a large capital project is included, according to a 2018 Chemical Engineering Progress article.

Is lump sum ever used in turnarounds?

Yes, for well-defined packages and for capital projects executed during the outage. It is rarely used for the turnaround as a whole because of discovery work.

Sources

  1. [1] Tim Olsen, Emerson — Turnarounds: Strategic opportunities to improve, Chemical Engineering Progress (Aug 2018)
  2. [2] Reliability Academy — Why do maintenance shutdowns overrun? The 6 real causes (Aug 24, 2026), citing AP-Networks
  3. [3] BIC Magazine — Quality work scopes imperative for turnaround success (Aug 2015)
  4. [4] Rimkus — Navigating NEC4 Option C: A contractor’s guide to practical realities and pitfalls
  5. [5] NEC — NEC4 Engineering and Construction Contract, Option C: target contract with activity schedule

All sources accessed November 16, 2026. General information, not legal advice. Figures are as published by each source.